Manage a Construction Project in Trello

Plan an office renovation using Agile methods, Kanban boards, and risk registers.

Introduction

30 Second Summary

Every construction project, from a kitchen remodel to a high-rise, lives or dies by how well someone plans and tracks the work. The tools and methods that keep real projects on schedule are the same ones you can learn today for free.

In this project, you will plan and manage a simulated office renovation using Trello and Agile methods. You will create the exact portfolio artifacts that hiring managers look for when evaluating project management candidates.

What You'll Build

You will build a complete project management portfolio for a $150,000 office renovation, including a Trello Kanban board, project charter, risk register, and stakeholder status report.

By the end of this project, you'll have:

  • A project charter defining scope, budget, timeline, and stakeholders for the office renovation.
  • A fully configured Trello Kanban board with 5 workflow lists, 15+ detailed task cards, and a simulated sprint workflow.
  • A risk register and stakeholder status report ready to present in PM interviews.
  • A Butler automation that auto-flags overdue tasks and keeps your board running without manual effort.

Are there any prerequisites?

No prior project management experience or tools are needed. This guide walks you through setting up everything from scratch, including your Trello account and documents. All tools used in this project are completely free.

Set Up Your Trello Account and Workspace

Managing a 12-week renovation with 15+ tasks, multiple stakeholders, and a $150,000 budget requires more than a to-do list. You need a visual system that shows where every task stands at a glance.

Trello is a project management tool built around Kanban boards. You organize tasks as cards on a board and drag them between columns as work progresses. In this step, you will create your Trello account and set up a dedicated Workspace and board for your renovation project.

In this step, get ready to:
  • Create a Trello account.
  • Set up a Workspace to organize your project boards.
  • Create the Office Renovation Project board.

Why Trello instead of Jira or Asana?

Trello is the most beginner-friendly PM tool with an intuitive drag-and-drop interface. Its free plan is the most generous for this use case: unlimited cards, up to 10 boards per Workspace, and 250 automation runs per month.

Jira is built for software development teams and has a steeper learning curve. Asana's free plan limits you to 2 users. Trello is widely recognized in job postings alongside both tools, so learning it builds transferable skills.

Create a Trello account
  • In your web browser, go to trello.com.
  • Click Sign up on the homepage.
  • Choose your signup method. You can use your email address, Google account, or Microsoft account.
  • Follow the prompts to complete your registration.

What will I see during signup?

Trello is owned by Atlassian, so the signup flow creates an Atlassian account. You may be asked to verify your email address before you can log in. If you use Google or Microsoft, the process is faster since it skips email verification.

Not receiving a verification email?

  • Check your spam or junk folder.
  • Make sure you entered the correct email address during signup.
  • Try signing up with a Google or Microsoft account instead, which skips email verification entirely.

Help me troubleshoot my Trello signup

Create a new Workspace

After signing up, Trello prompts you to create a Workspace. A Workspace is a container that holds all your related project boards in one place.

  • In the Workspace name field, type PM Portfolio.
  • For the Workspace type, select Other.
  • Click Continue to create your Workspace.

Why name it PM Portfolio?

This Workspace will hold any project boards you create for your portfolio. Naming it clearly helps you stay organized if you add more boards in the future. Trello's free plan supports up to 10 boards per Workspace, so you have plenty of room to grow.

Trello may also ask you to invite team members or answer a few onboarding questions. You can skip these prompts for now by clicking Skip or closing the dialog.

Create your project board

Your Workspace is ready. Now you will create the board where all your renovation tasks will live.

  • Click the Create button in the Trello header bar at the top of the page.
  • Select Create board.
  • In the Board title field, type Office Renovation Project.
  • Confirm that PM Portfolio is selected as the Workspace.
  • Click the Visibility dropdown and select Private.
  • Choose any background color or image you like.
  • Click Create to finish.

You should see your new empty board with the title Office Renovation Project at the top. The board has no lists or cards yet.

Why set the board to Private?

A Private board is only visible to people you explicitly invite. In a real project, this keeps sensitive information like budgets and contractor details secure. You can always change visibility later if you need to share the board with teammates.

Don't see the Create button?

  • The Create button is a blue plus (+) icon in the top header bar, next to the Trello logo and your Workspace name.
  • If you are on a mobile device, the layout may look different. Use a desktop or laptop browser for the best experience.

Help me find where to create a board in Trello

Your Trello board is ready to go. Next up, you will write a project charter that defines the scope, budget, timeline, and stakeholders for your renovation project.

Write Your Project Charter

Your Trello workspace and board are set up and ready to go. Before you start building tasks on the board, every well-run project needs a foundational planning document that defines what the project is, who is involved, and what success looks like.

That document is the project charter. In this step, you will create one for the office renovation project using Google Docs or Microsoft Word.

In this step, get ready to:
  • Create a project charter document with all required sections.
  • Fill in the charter details using the office renovation scenario.
  • Review and save the completed charter.
Create the charter document

What is a project charter?

A project charter is a short document that formally authorizes a project and gives the project manager authority to spend resources. It captures the project's purpose, scope, stakeholders, timeline, and budget in one place.

Hiring managers love seeing charters because they prove you can think through a project before jumping into execution.

  • Open Google Docs at docs.google.com or open Microsoft Word.
  • Create a new blank document.
  • Type Project Charter: Office Renovation as the document title at the top.
  • Add the following section headings to your document, each on its own line:
  • Project Name.
  • Project Manager.
  • Project Sponsor.
  • Start Date.
  • End Date.
  • Budget.
  • Project Objective.
  • Scope (with sub-sections: In-Scope and Out-of-Scope).
  • Key Stakeholders.
  • Key Milestones.
  • Success Criteria.

Pro tip: use heading styles

Format each section name as a Heading 2 in your document. This creates a professional look and makes the charter easy to scan.

Fill in the charter details

Now populate each section using the office renovation scenario. Follow the details below exactly so your charter matches the project you will build in Trello.

  • Under Project Name, type Office Renovation.
  • Under Project Manager, type your full name.
  • Under Project Sponsor, type Sarah Chen, VP of Operations.
  • Under Start Date, type May 5, 2026.
  • Under End Date, type July 27, 2026.
  • Under Budget, type $150,000.
  • Under Project Objective, type the following: "Renovate the 2,000 sq ft office space to create an open-plan layout with 3 meeting rooms, a break room, and 30 workstations."
  • Under In-Scope, list the following eight items: demolition, electrical work, plumbing, HVAC updates, flooring, painting, furniture installation, and IT infrastructure setup.
  • Under Out-of-Scope, list the following three items: exterior work, parking lot modifications, and landscaping.

Why define out-of-scope items?

Listing what is NOT included is just as important as listing what is. Out-of-scope items prevent scope creep by setting clear boundaries upfront.

If a stakeholder later asks about parking lot changes, you can point to the charter and say it was agreed to be out of scope.

  • Under Key Stakeholders, list these five people:
  • Under Key Milestones, list these five project dates:
  • Under Success Criteria, type the following: "Project delivered within $150,000 budget, completed by July 27, passes building inspection, and achieves 80% employee satisfaction in post-move survey."
Review and save your charter

Your charter should now have all 11 sections filled in. A quick review ensures nothing was missed before you move on.

  • Read through the document from top to bottom.
  • Confirm that every section has content and no headings are left blank.
  • Save the document.
  • Keep the document open in a separate browser tab. You will reference it when building your Trello board in the next step.

Your charter is a living document

In a real project, the charter evolves as new information surfaces. Scope changes, budget adjustments, and timeline shifts all get reflected back in the charter.

You will see this in action later when you handle a scope change request.

Not sure if your charter is complete?

Count your section headings. You should have exactly 11 (Project Name through Success Criteria). If any section is missing or blank, scroll back through the instructions above to find the details for that section.

Help me check if my project charter has all the required sections.

Your project charter is complete. Next up, you will build the Kanban board in Trello and create the workflow lists that bring this plan to life.

Build Your Kanban Board and Workflow

Your project charter defines what the renovation project looks like on paper. Now it is time to turn that plan into a visual workflow you can actually manage day to day.

A Kanban board organizes work into columns that represent stages of progress. In this step, you will build your board's structure, set up color-coded labels, and fill your project backlog with tasks.

In this step, get ready to:
  • Create 5 workflow lists that represent each stage of your project.
  • Configure color-coded labels for task categories and priorities.
  • Add 15 task cards to your Backlog representing the full renovation scope.
Create the workflow lists

Every Kanban board needs columns that represent the stages work moves through. Your board will have 5 lists, from initial planning all the way through to completion.

  • Open your Office Renovation Project board in Trello.
  • Click Add a list on the right side of your board.
  • Type Backlog and press Enter.
  • Click Add a list again (it appears to the right of your new list).
  • Type To Do (This Sprint) and press Enter.
  • Repeat for the remaining 3 lists, pressing Enter after each:
  1. In Progress.
  2. Review/Approval.
  3. Done.

You should now see 5 empty lists arranged from left to right across your board.

What does each list represent?

  • Backlog holds all tasks that need to be done but have not been scheduled yet.
  • To Do (This Sprint) contains tasks the team has committed to completing in the current sprint cycle.
  • In Progress is for tasks someone is actively working on right now.
  • Review/Approval holds completed work that needs sign-off from a stakeholder or inspector.
  • Done is for fully completed and approved tasks.

Lists in the wrong order?

You can drag and drop list headers to rearrange them. Click and hold a list's title bar, then drag it left or right to the correct position.

Help me rearrange my Trello lists into the correct order.

Set up labels for task categories

Labels give you a color-coded system for categorizing tasks at a glance. You will create labels for both priority levels and work categories so each card tells you two things at once.

To access label settings, you need to open a card first. You will create a temporary card for this purpose.

  • Click Add a card at the bottom of the Backlog list.
  • Type temp and press Enter.
  • Click on the temp card to open it.
  • Click Labels in the Add to card section on the right side of the card.
  • Click the pencil icon next to the red color swatch.
  • Type Blocked in the name field.
  • Click Save.

Repeat the pencil-icon-then-rename process for the remaining 6 labels:

  • Orange: High Priority.
  • Yellow: Medium Priority.
  • Green: On Track.
  • Blue: Design.
  • Purple: Construction.
  • Dark green: IT/Infrastructure.
  • Close the label editor by clicking the X in the top right of the labels popup.
  • Close the temp card.
  • Hover over the temp card in the Backlog list and click the pencil icon that appears.
  • Click Archive to remove it from your board.

Why both priority and category labels?

Priority labels (red, orange, yellow, green) tell you how urgent a task is. Category labels (blue, purple, dark green) tell you what type of work it involves.

Each card can have multiple labels at once. This means you can see at a glance that a task is both high priority and construction-related.

Can't find the pencil icon to rename labels?

Make sure you are clicking the small pencil icon next to each color swatch, not the color itself. Clicking the color just applies the label to the card without letting you rename it.

Help me rename the color labels on my Trello board.

Add task cards to the Backlog

The Backlog is the master list of every task your project needs. You will add 15 cards that cover the full scope of the renovation, straight from your project charter.

  • Click Add a card at the bottom of the Backlog list.
  • Type Finalize floor plan design and press Enter.
  • Trello keeps the card input open after pressing Enter, so you can type the next card name immediately.
  • Add the remaining 14 cards one by one, pressing Enter after each:
  1. Get building permits.
  2. Hire electrical subcontractor.
  3. Demolish existing walls.
  4. Install new electrical wiring.
  5. Update HVAC system.
  6. Install plumbing for break room.
  7. Lay new flooring.
  8. Paint all rooms.
  9. Install meeting room partitions.
  10. Set up network cabling.
  11. Install workstations and furniture.
  12. Set up Wi-Fi and server room.
  13. Final building inspection.
  14. Employee move-in coordination.
  • Click the X or click outside the card input area to close it once all 15 cards are added.

Your Backlog list should now show 15 cards stacked vertically. The other 4 lists remain empty.

Why start everything in the Backlog?

In Agile project management, the backlog is your single source of truth for all work that needs to happen. Tasks only move to other lists when the team commits to working on them during a sprint.

This prevents teams from overcommitting. Instead of trying to do everything at once, you pull tasks from the backlog in priority order.

Cards appearing in the wrong list?

Make sure you clicked Add a card at the bottom of the Backlog list specifically. If a card ended up in the wrong list, click and drag it into the Backlog column.

Help me move Trello cards between lists.

Pro tip: count your cards

Scroll through your Backlog and count the cards to make sure you have all 15. Missing a card now means missing a task later in the project.

Your Kanban board now has a solid structure with 5 workflow stages and a full backlog of 15 tasks. Next up, you will add rich detail to your task cards with descriptions, checklists, and due dates.

Add Detail to Your Task Cards

Your Kanban board now has 5 workflow lists and 15 task cards sitting in the Backlog. That is a great start, but a card with just a title does not tell anyone what the task actually involves, when it is due, or who is responsible for it.

In this step, you will bring your task cards to life by adding descriptions, labels, due dates, checklists, and team assignments. These details turn a simple card into a complete work package that any team member can pick up and execute.

In this step, get ready to:
  • Add descriptions, labels, and due dates to your task cards.
  • Create checklists to break down complex tasks into subtasks.
  • Assign members and practice stakeholder communication with comments.
Add descriptions, labels, and due dates

Every task card needs three things to be actionable: a description explaining what the work involves, labels for quick visual categorization, and a due date tied to the project timeline. You will start with one card in full detail, then repeat the process for five more.

  • Click on the card Finalize floor plan design in your Backlog list to open it.
  • Click the Description area below the card title.
  • Type the following description into the text area:
Work with architect to finalize the open-plan layout. Must include 3 meeting rooms (8-person, 6-person, 4-person), break room with kitchenette, and 30 workstations. Deliver final blueprints for contractor review.
  • Click Save to save the description.
  • Click Labels in the Add to card section on the right side of the card.
  • Select the Blue label (Design).
  • Select the Orange label (High Priority).
  • Close the labels menu by clicking the X in the top right corner of the menu.
  • Click Dates in the Add to card section.
  • Select May 16, 2026 as the due date.
  • Click Save to set the date.

You should now see the Blue and Orange labels displayed across the top of the card. The due date appears near the bottom.

What do descriptions, labels, and due dates do?

  • Descriptions define the scope of work so any team member can pick up the card and know exactly what to deliver.
  • Labels give you a color-coded visual system. You can scan the entire board at a glance to spot priorities and categories.
  • Due dates keep the project on schedule. Trello sends a notification 24 hours before a card's due date, so nothing slips through the cracks.

Can't find the Labels or Dates buttons?

Make sure you have clicked on the card to open it fully. The Labels and Dates buttons are in the Add to card section on the right side of the card detail view, not on the board itself.

Help me find the Add to card section in Trello

Now repeat this process for at least 5 more cards. Use your project charter milestones to pick appropriate due dates for each card.

  • Open each card, write a 1-3 sentence description explaining the work involved.
  • Add labels that match the card's category (Blue for design tasks, Purple for construction, Dark Green for IT/infrastructure).
  • Add the Orange (High Priority) label to any card on the project's critical path.
  • Set due dates based on the milestone timeline in your project charter.

Pro tip: suggested card assignments

Here are suggested labels and due dates for 5 cards. Your charter milestones are the best guide for picking dates.

  • Get building permits: Purple (Construction) + Orange (High Priority). Due: May 12, 2026.
  • Hire electrical subcontractor: Purple (Construction) + Orange (High Priority). Due: May 19, 2026.
  • Install new electrical wiring: Purple (Construction). Due: June 6, 2026.
  • Set up network cabling: Dark Green (IT/Infrastructure). Due: June 20, 2026.
  • Final building inspection: Orange (High Priority). Due: July 17, 2026.
Add checklists to complex tasks

Some tasks are too big to track as a single card. A checklist lets you break a complex task into smaller subtasks without creating separate cards for each one. This is especially useful for multi-day tasks like demolition that involve several sequential activities.

  • Click on the card Demolish existing walls in your Backlog list.
  • Click Checklist in the Add to card section on the right.
  • Type Demolition Tasks as the checklist name.
  • Click Add to create the checklist.
  • Type the first checklist item: Disconnect electrical in demolition zones.
  • Press Enter to save the item and move to the next line.
  • Add the second item: Remove furniture and equipment.
  • Add the third item: Set up dust barriers.
  • Add the fourth item: Demolish marked walls.
  • Add the fifth item: Haul debris to dumpster.
  • Add the sixth and final item: Site cleanup and inspection.

You should see a progress bar appear on the card showing 0 of 6 items complete. As items get checked off during the project, this bar fills up to give you an instant snapshot of task completion.

Why use checklists instead of separate cards?

Checklists are perfect for subtasks that belong together under one responsibility. If you created a separate card for each demolition subtask, your board would balloon from 15 cards to 25+. That makes it harder to see the big picture.

The rule of thumb: if a subtask needs its own labels, due date, or assigned member, promote it to a full card. If it just needs a checkbox, keep it in a checklist.

Checklist items not saving?

Make sure you press Enter after typing each item. If you click away from the text field without pressing Enter, the item may not be saved. You can also click the Add button to confirm each item.

My checklist items are disappearing when I try to add them

Add members and simulate team assignments

On a real project, you would assign each card to the team member responsible for completing it. You would also use card comments to communicate with stakeholders directly on the relevant task. Since this is a solo project, you will add yourself as a member and write a comment that simulates real stakeholder communication.

  • Click on any card in the Backlog list to open it.
  • Click Members in the Add to card section on the right.
  • Click your name to add yourself as a member of the card.
  • Close the members menu.
  • Repeat this for at least 4 more cards so that several cards show your avatar on them.

You should see your profile avatar appear on the front of each card you assigned yourself to, visible right from the board view.

Now you will simulate stakeholder communication by adding a comment on a card.

  • Click on the card Set up network cabling in your Backlog list.
  • Scroll down to the Activity section at the bottom of the card.
  • Click the Write a comment... text area.
  • Type the following comment:
@Lisa Wong Please confirm server room specifications by May 20.
  • Click Save to post the comment.

Your comment now appears in the card's activity feed with a timestamp. In a real project with team members added to the board, the @mention would send Lisa Wong a notification.

Why communicate directly on the card?

Keeping communication on the card creates a paper trail tied to the specific task. When a hiring manager or team member opens this card weeks later, they can see the full history of decisions, requests, and updates in one place. This is far more effective than scattered emails or chat messages that get buried over time.

Don't see the Activity section?

The Activity section is at the very bottom of the card detail view. You may need to scroll down past the description and any checklists. If you see a Show Details link, click it to expand the activity feed.

Help me find where to write a comment on a Trello card

Your task cards are now packed with the details a real project team needs to get work done. Next up, you will put these cards to work by running a simulated sprint and handling a curveball from your project sponsor.

Run a Simulated Sprint and Handle a Scope Change

Your Trello board now has 15 detailed task cards sitting in the Backlog. The board is organized, but completely static. A real project board comes to life when tasks start moving through workflow stages.

In this step, you will run your first sprint by dragging tasks through your Kanban workflow. You will also face something every project manager deals with: a mid-project scope change from your sponsor.

In this step, get ready to:
  • Plan Sprint 1 by selecting tasks from the Backlog.
  • Simulate task progress by moving cards through workflow stages.
  • Handle a scope change request with full impact documentation.
Plan Sprint 1

In Agile project management, a sprint is a fixed time period where the team commits to completing a specific set of tasks. For this project, Sprint 1 covers Weeks 1 through 4 of the renovation.

What is sprint planning?

Sprint planning is when the team reviews the Backlog and selects tasks they can realistically complete within the sprint timeframe. The goal is to avoid overloading the team while keeping the project on schedule.

  • On your Office Renovation Project board, find the Backlog list on the far left.
  • Click and drag the card Finalize floor plan design from Backlog to the To Do (This Sprint) list.
  • Drag Get building permits from Backlog to To Do (This Sprint).
  • Drag Hire electrical subcontractor from Backlog to To Do (This Sprint).
  • Drag Demolish existing walls from Backlog to To Do (This Sprint).

Your To Do (This Sprint) list should now contain 4 cards. These represent the work your team has committed to for Weeks 1 through 4.

Cards not showing up in the right list?

Make sure you are dragging each card to the correct list. The card should snap into the destination list when you release it. If a card ends up in the wrong list, just drag it again to the correct one.

Help me move cards between lists on my Trello board.

Simulate task progress

With Sprint 1 planned, it is time to simulate work happening. In a real project, tasks move through workflow stages as the team completes work and gets approvals.

  • Drag Finalize floor plan design from To Do (This Sprint) to In Progress.
  • Drag Finalize floor plan design from In Progress to Review/Approval. The architect has submitted the design for sponsor review.
  • Drag Finalize floor plan design from Review/Approval to Done. Sarah Chen approved the floor plan.

What just happened?

You just moved a single card through every stage of your Kanban workflow. This is the core pattern: tasks flow from left to right as work gets done and reviewed. In a real project, you would update the board daily as the team reports progress in standups.

Now simulate progress on the remaining Sprint 1 tasks.

  • Click on the Demolish existing walls card to open it.
  • In the Demolition Tasks checklist, check off the first three items: Disconnect electrical in demolition zones, Remove furniture and equipment, and Set up dust barriers.
  • Close the card by clicking the X in the top right corner of the card window.
  • Drag Demolish existing walls from To Do (This Sprint) to In Progress. The prep work is done and actual demolition is underway.
  • Drag Get building permits from To Do (This Sprint) to In Progress. The permits have been submitted and are awaiting city approval.

Your board should now show Finalize floor plan design in Done, two cards in In Progress, and one card remaining in To Do (This Sprint).

Why is visualizing workflow important?

This left-to-right flow is the core of Kanban. It gives the entire team instant visibility into what is queued, what is actively being worked on, and what is complete. When a hiring manager sees a board like this, they know you understand how real teams track work.

Checklist items not checking off?

Make sure you click directly on the checkbox square to the left of each item. Clicking the text itself will not toggle the checkbox. If the checklist does not appear, open the card and scroll down to find it below the description.

Help me check off items in my Trello checklist.

Handle a mid-sprint scope change

Scope changes happen on almost every project. Scope management is the PM skill of evaluating change requests, documenting their impact, and making sure the team adjusts accordingly.

Here is the scenario: Sarah Chen (your project sponsor) requests adding a private phone booth to the office layout in Week 3. This was not in the original plan, so you need to treat it as a formal scope change.

  • Go to the Backlog list on your board.
  • Click Add a card at the bottom of the Backlog list.
  • Type SCOPE CHANGE: Add private phone booth as the card name and press Enter.
  • Click on the new card to open it.

Now add the impact analysis to the card description. A good scope change record captures who requested it, what the impact is, and what decision was made.

  • Click the Description area on the card and type the following:
Requested by Sarah Chen on Week 3.
Impact: Additional $8,000 cost, 3-day schedule delay.
Requires architect revision and additional electrical work.
Decision: Approved with budget adjustment from contingency fund.

Why document scope changes this way?

Every scope change needs a paper trail. By recording who requested it, the cost and schedule impact, and the approval decision, you protect both yourself and the project. If the budget runs tight later, this documentation shows exactly where the extra cost came from.

  • Click Labels from the Add to card section on the right side of the card.
  • Select the Orange (High Priority) label.
  • Select the Blue (Design) label.
  • Close the labels menu by clicking the X or clicking outside of it.

Finally, add a comment documenting the formal change request and decision.

  • Scroll down to the Activity section at the bottom of the card.
  • Type the following comment in the text box and click Save:
Change Request: Sarah Chen requested a private phone booth be added to the office layout.
Impact Analysis: $8,000 additional cost, 3-day schedule delay. Requires architect revision to floor plan and additional electrical work.
Approval: Approved by sponsor. Budget adjusted using contingency fund.
  • Close the card by clicking the X in the top right corner.

The scope change also affects your current sprint. The phone booth requires an architect revision before electrical work can be planned. That means hiring the electrical subcontractor is no longer actionable this sprint.

  • Drag Hire electrical subcontractor from To Do (This Sprint) back to the Backlog. It will be re-prioritized in a future sprint once the revised floor plan is ready.

Why move a card back to the Backlog?

This is a common real-world PM move. When a scope change creates a dependency that blocks a task, you pull that task out of the current sprint. Leaving a blocked card in the sprint creates a false picture of how much work the team can actually deliver.

Your board should now show the To Do (This Sprint) list empty. In Progress has Demolish existing walls and Get building permits. Done has Finalize floor plan design. The Backlog now has your new scope change card alongside the remaining tasks.

Board layout doesn't match?

Double-check that all four original Sprint 1 cards have been moved out of To Do (This Sprint). Hire electrical subcontractor should be back in the Backlog. If any card is in the wrong list, drag it to the correct one.

Help me check that my Sprint 1 board state is correct.

Your sprint simulation is complete. You now have a board that tells a story of real project work: tasks planned, progress tracked, and a scope change handled professionally. Next up, you will build a risk register to prepare for the things that could go wrong.

Create a Risk Register

In the last step, you ran your first sprint and handled a scope change request. Your Trello board now shows tasks flowing through the Kanban workflow, and you've documented a real scope decision.

Every construction project carries risks that can blow up timelines and budgets. In this step, you'll build a risk register directly on your Trello board to identify, assess, and plan for the top threats to your renovation project.

In this step, get ready to:
  • Create a Risk Register list on your Trello board.
  • Add 5 risk cards with categories, probability/impact ratings, and mitigation strategies.
  • Color-code risks by priority for quick visual scanning.
Create a new Trello list for risks

Your risk register needs its own dedicated space on the board, separate from your task workflow lists.

  • On your Office Renovation Project board, click Add a list to the right of your Done list.
  • Name the new list Risk Register and press Enter.

You should now see 6 lists on your board, with Risk Register on the far right.

What is a risk register?

A risk register is a structured log that tracks all identified project risks. Each risk includes a description, probability rating, impact rating, response strategy, and an assigned owner.

It's one of the most referenced artifacts in PM interviews because it shows you can think ahead and plan for problems before they happen.

Add risk cards with full details

Professional risk registers use an "If...then" format to describe risks. This connects each cause directly to its project impact, making the risk specific and actionable.

You'll create 5 risk cards covering common construction project threats. The first card gets a full walkthrough. Cards 2 through 5 follow the same process.

Add your first risk card (R-001)
  • Click Add a card at the bottom of the Risk Register list.
  • Type the following card name and press Enter:
R-001: If building permits are delayed, then project start is pushed back 2+ weeks
  • Click on the card to open it.
  • Click in the Description field and enter the following details:
Category: Schedule
Probability: Medium
Impact: High
Priority: High
Response Strategy: Mitigate
Mitigation: Submit permits 3 weeks early, maintain contact with city inspector.
Owner: James Park
Status: Open
Review Date: Weekly
  • Click Save to close the description editor.

What do these risk fields mean?

  • Category is the area of the project this risk affects (Schedule, Budget, Resource, Technical, Safety).
  • Probability/Impact rates how likely the risk is and how severe the consequences would be.
  • Response Strategy is your plan of action. The four standard strategies are Mitigate (reduce likelihood), Transfer (shift to another party), Avoid (eliminate the risk), and Accept (acknowledge and monitor).
  • Owner is the person responsible for monitoring this risk and executing the mitigation plan.

Why the "If...then" format?

Vague risk descriptions like "permit problems" don't tell the team what to watch for or what happens if the risk materializes. The "If...then" format forces you to name the specific trigger and the specific consequence.

This is a professional standard used across construction and tech project management. Interviewers will recognize it immediately.

Add the remaining four risk cards (R-002 through R-005)

Follow the same process for each card below. Click Add a card in the Risk Register list, type the card name, open the card, and paste the description.

  • Create a card with this name:
R-002: If subcontractor availability is limited, then construction timeline extends
  • Open the card and enter this description:
Category: Resource
Probability: High
Impact: Medium
Priority: High
Response Strategy: Mitigate
Mitigation: Identify 2 backup contractors before project start.
Owner: Tom Nguyen
  • Click Save on the description, then create the next card with this name:
R-003: If material costs exceed estimates, then budget overrun occurs
  • Open the card and enter this description:
Category: Budget
Probability: Medium
Impact: High
Priority: High
Response Strategy: Mitigate
Mitigation: Lock in material prices with suppliers early, maintain 10% contingency.
Owner: James Park
  • Click Save on the description, then create the next card with this name:
R-004: If asbestos is found during demolition, then work stops for remediation
  • Open the card and enter this description:
Category: Technical/Safety
Probability: Low
Impact: Very High
Priority: High
Response Strategy: Transfer
Mitigation: Include asbestos clause in contractor agreement, hire environmental assessment before demolition.
Owner: Tom Nguyen

Why is this risk's response strategy "Transfer" instead of "Mitigate"?

Asbestos remediation requires specialized, licensed professionals. You can't reduce the likelihood or handle it yourself. By including an asbestos clause in the contractor agreement, you transfer the financial and operational responsibility to the contractor and their insurance.

  • Create the final risk card with this name:
R-005: If IT infrastructure setup is delayed, then employee move-in is postponed
  • Open the card and enter this description:
Category: Technical
Probability: Medium
Impact: Medium
Priority: Medium
Response Strategy: Mitigate
Mitigation: Order equipment 6 weeks in advance, create parallel IT setup schedule.
Owner: Lisa Wong
  • Click Save on the description.

Your Risk Register list should now contain 5 cards, each with a descriptive "If...then" title and a structured description.

Cards in the wrong list?

If you accidentally created a card in the wrong list, drag it from that list into the Risk Register list. You can also click on the card, select Move from the Actions menu on the right, and choose the correct list.

Help me move my Trello cards to the right list.

Add labels and color-code risk priority

Color-coded labels let you scan the risk register at a glance and spot which risks need the most attention. You'll use the labels you set up earlier in the project.

  • Click on the R-001 card to open it.
  • Click Labels from the Add section on the right side of the card.
  • Select the Red label (Blocked). This marks it as a High priority risk.
  • Click the X to close the label picker.
  • Repeat this process for R-002, R-003, and R-004. Add the Red (Blocked) label to each of these High priority risks.
  • Open the R-005 card.
  • Click Labels and select the Yellow label (Medium Priority) instead of Red.

Your Risk Register list should now show color-coded labels on each card. Four cards have a Red label and one card has a Yellow label.

Why color-code risks?

In a real project, you'd review the risk register in weekly team meetings. Color-coding lets everyone in the room immediately see which risks are critical without reading every card's description.

This is the same principle behind traffic-light status reporting (Red/Yellow/Green) used across the PM industry.

Don't see label colors on your cards?

Trello shows labels as thin color bars by default. Click on any color bar on a card to expand all labels and show their text names. Make sure you selected the correct color when adding the label.

Help me fix my Trello labels.

Your risk register is complete. You now have 5 categorized, rated, and color-coded risks with owners and mitigation plans. Next up, you'll pull everything together into a stakeholder status report that communicates your project's health to leadership.

Write a Stakeholder Status Report

Your risk register is complete. You now have a structured way to track and manage threats across the renovation project.

The final piece of your PM portfolio is a stakeholder status report. This weekly document keeps sponsors and team leads aligned on progress, risks, and decisions that need their input.

In this step, get ready to:
  • Create a status report document with professional section headings.
  • Fill in the report using data from your Trello board.
  • Review and save the report as a portfolio-ready artifact.
Create the status report document

A good status report follows a consistent structure so stakeholders always know where to find the information they care about. You will set up the document with standard sections first, then fill in the data.

  • Open Google Docs at docs.google.com or open Microsoft Word.
  • Create a new blank document.
  • Title the document Weekly Status Report: Office Renovation Project - Week 4.
  • Add each of the following as section headings in your document:
  • Report Date.
  • Project Name.
  • Project Manager.
  • Overall Status (Green/Yellow/Red).
  • Summary.
  • Completed This Week.
  • In Progress.
  • Planned for Next Week.
  • Risks and Issues.
  • Budget Status.
  • Key Decisions Needed.

What is a stakeholder status report?

A stakeholder status report is a recurring document that summarizes project health for decision-makers. It covers what was accomplished, what is in progress, upcoming work, active risks, and any decisions that need stakeholder input.

Most project managers send these weekly. The consistent structure means stakeholders can scan it quickly instead of reading through every detail.

Fill in the report using your Trello board data

Your Trello board is the source of truth for this report. Every section maps to something visible on your board.

  • Under Report Date, type May 30, 2026.
  • Under Project Name, type Office Renovation.
  • Under Project Manager, type your name.
  • Under Overall Status, type Yellow.

What does Green, Yellow, and Red status mean?

Project managers use a RAG system (Red, Amber/Yellow, Green) to communicate project health at a glance. Green means on track. Yellow means there are concerns or minor issues. Red means the project is at serious risk.

The scope change for the phone booth shifted this project from Green to Yellow. The added cost and schedule delay are manageable, but stakeholders need to know about them.

Now fill in the narrative sections. These are the parts stakeholders pay the most attention to.

  • Under Summary, type: "Sprint 1 is 75% complete. Floor plan design approved. Demolition in progress. Building permits pending. A scope change request for a private phone booth was approved, adding $8,000 and 3 days to the timeline."
  • Under Completed This Week, type: "Finalize floor plan design (approved by Sarah Chen)."
  • Under In Progress, type: "Demolish existing walls (60% complete). Get building permits (submitted, awaiting approval)."
  • Under Planned for Next Week, type: "Complete demolition. Receive building permits. Begin electrical subcontractor onboarding."

Where does this data come from?

Look at your Trello board. The "Completed This Week" section maps to cards in your Done list. The "In Progress" section maps to cards in your In Progress list. The "Planned for Next Week" items come from cards still in your Backlog that are scheduled for the next sprint.

This is why a well-maintained Kanban board makes reporting fast. The board is always up to date, so writing the report is just translating what you see.

  • Under Risks and Issues, type: "R-001: Building permits pending (medium risk, being tracked weekly). R-002: Subcontractor scheduling (being monitored, backup contractors identified)."
  • Under Budget Status, type: "$12,000 spent of $150,000 budget. $8,000 scope change approved from contingency fund."
  • Under Key Decisions Needed, type: "Confirm meeting room AV equipment specifications by Week 5."

Pro tip: use risk IDs

Notice how the Risks and Issues section references R-001 and R-002 from your risk register. Using consistent risk IDs across documents makes it easy for stakeholders to cross-reference the full risk details when they need more context.

Review and connect it to your portfolio

A hiring manager reading this report should immediately understand the project status, what risks exist, and what decisions need their attention. That clarity is what separates a strong PM candidate from someone who just lists tools on a resume.

  • Read through the report from top to bottom.
  • Check that every section is filled in and that the data matches what you see on your Trello board.
  • Verify that the Completed This Week section matches the cards in your Done list on Trello.
  • Verify that the In Progress section matches the cards in your In Progress list on Trello.
  • Save the document.

Your PM portfolio is complete

You now have three artifacts that work together as a professional PM portfolio:

  • A project charter that defines scope, budget, timeline, and stakeholders.
  • A Trello Kanban board with workflow lists, labeled cards, a risk register, and a simulated sprint.
  • A stakeholder status report that communicates project health clearly and professionally.

In an interview, you can walk a hiring manager through each document to demonstrate planning, tracking, risk management, and stakeholder communication skills.

Secret mission

Automate Your Board with Butler

Trello has a built-in automation tool called Butler that can automate repetitive tasks. Real project managers use automation to stay on top of deadlines without manually checking every card. Your mission: create three Butler automations that flag overdue cards, sort your sprint list daily, and complete tasks with a single click.

Before you go

Clean Up Your Resources

Decide whether to keep your resources running, pause them to come back later, or delete them entirely. This project uses Trello's free plan and free document editors, so there are no ongoing costs.

Resources you used:

  • Trello account (free tier).
  • Trello Workspace named "PM Portfolio."
  • Trello board named "Office Renovation Project" with 6 lists, 15+ cards, labels, checklists, and due dates.
  • Project Charter document in Google Docs or Word.
  • Weekly Status Report document in Google Docs or Word.
  • Butler automations (if you completed the Secret Mission).

Keep everything running

No action needed. Choose this if you are still actively building on your PM portfolio or plan to revisit the board to practice more.

  • Your Trello board, Workspace, and all cards will stay exactly where they are.
  • Your Google Docs or Word documents remain in your account.
  • Trello's free plan has no expiration, so your board will be available whenever you need it.

Pause - I'll come back to this later

Keep your files and board but disable any active automations to avoid using up your monthly Butler runs.

  • Open your Trello board and click Automation in the board header.
  • Disable any active Butler rules or calendar commands by toggling them off. This prevents them from consuming your 250 free command runs per month.
  • Your board, cards, documents, and Workspace will remain intact for when you return.

Delete - I don't want to use this again

Remove all project resources and start fresh. Make sure you have saved any screenshots you want for your portfolio before deleting.

  • Open your "Office Renovation Project" board in Trello.
  • Click the three-dot menu (...) in the board header, then select Close board.
  • After closing the board, click Permanently delete board to remove it entirely.
  • To delete the Workspace, go to your Workspace settings and select Delete this Workspace.
  • Delete your Project Charter and Weekly Status Report documents from Google Docs or Word if you no longer need them.
  • If you want to delete your Trello account entirely, go to trello.com, click your profile icon, select Settings, and look for the option to delete your account.

Mission accomplished

Nice Work!

Congratulations! You just planned and managed a construction project like a professional PM. You now have a portfolio-ready Trello board, project charter, risk register, and stakeholder status report that demonstrate exactly the skills hiring managers look for.

Here is what you accomplished:

  • Built a Kanban board in Trello with 5 workflow stages, 15+ detailed task cards, and a full sprint simulation that included moving tasks through the workflow.
  • Created portfolio-ready PM documents including a project charter, risk register with 5 categorized risks, and a stakeholder status report that communicates project health at a glance.
  • Practiced real-world scope management by handling a mid-sprint change request with impact analysis and documentation.
  • Automated your board with Butler rules to flag overdue tasks and complete cards with a single click.